Sl no | Name of work | Description | AS details | TS details | Agreement No. with date | Name of Contractor & Contract value as per agreement | Date of Completion as per agreement | Expected date of completion | Current status | Officer in Charge |
1 | Repair / Maintenance Works at Thevara | Repair works for store | Order No. KSINC/85/2022 dated:19/03/2022 for Rs. 2 Lakh | Order No. KSINC/30/2022 dated:22/03/2022 for Rs. 2 Lakh | Agreement to be executed | M/s AIM Assosicates Rs 1.83 Lakhs |
TOC- 45 days | Work Completed , Revised AS sanctioned,Bill Paid | ||
2 | Renovation Works of KSINC Head Office | General maintenance of Head Office building | Order No. KSINC/1267/2021 dated: 14/01/2022 for 27.05 Lakhs | Order No. KSINC/25/2022 dated 27/01/2022 for Rs. 27.05 Lakhs | Agreement No. 19/KSINC/2021-22 Dated 30/03/2022 | Mr. A.F Jenson Rs.18.46 Lakhs |
TOC- 6 months.Site handed over 08/04/2022 | Work Completed.Bill Paid. | ||
3 | Providing Mooring Pile at Thevara and Marine Drive | Casting of RCC piles for mooring purpose of barges/vessels | ORDER No. KSINC/1310/2021 Dated:30/09/2021 for Rs. 29.50 Lakhs | Order No. KSINC/17/2021 dated 20/10/2021 for Rs.29.50 Lakhs | Agreement No: 05/KSINC/2022-23 dated 02/04/2022 | Mr. Ciju John | TOC – 3 months from date of site handing over (12/04/2022) | 12-07-2022 | Work Completed on 12/07/2022.Final bill paid. | Melba Alias, Project Executive II |
Rs.28.97 Lakhs | ||||||||||
4 | Maintenance of Head Office Building | Furnishing of new office | ORDER No. KSINC/1508/2021 Dated:12/11/2021 for Rs. 8.47 Lakhs | Order No. KSINC/20/2021 dated 17/11/2021 for Rs. 8.47 Lakhs | Agreement No. 10/KSINC/2021-22 Dtd04/01/2022 | Mr. Ciju John | 14-03-2022 | 15-04-2022 | Work completed on 28/04/2022 . Bill paid on 25/07/2022 Rs.8,67,639/- | Melba Alias, Project Executive II |
Rs. 7.14 Lakhs | ||||||||||
5 | Office space arrangement at HO | Setting up of new office | ORDER No. KSINC/1509/2021 Dated:12/11/2021 for Rs.4.98 Lakhs | Order No. KSINC/19/2021 dated 17/11/2021 for Rs.4.98 Lakhs | Agreement No. 11/KSINC/2021-22 DATED 04/01/2022 | Mr. Ciju John | 14-03-2022 | 15-04-2022 | Work Completed on 29/04/2022.Bill paid for an amountof Rs.5,06,562.00/- | Susan K Santy, Project Executive III |
Rs. 4.30 Lakhs | ||||||||||
6 | Providing Air conditioning system at Second Floor, KSINC head office | Providing AC at newly furnished office | Order No. KSINC/58/2022 dated 17/02/2022 for Rs. 2.5 Lakhs | Order No. KSINC/27/2022 dated 18/02/2022 for Rs. 2.5 Lakhs | Work order no. KSINC/58/2022 dated 02/03/2022 | Work completed and bill settled. | Melba Alias, Project Executive II | |||
M/s Pinnacle Cooling Solutions | 11-03-2022 | |||||||||
Rs. 2.09 Lakhs | 17-03-2022 | |||||||||
7 | Renovation Works of KSINC Head Office – Local Area Networking works | Establishing Local Area Network | Order No. KSINC/1267/2021 dated: 14/01/2022 for 27.05 Lakhs | Order No. KSINC/25/2022 dated 27/01/2022 for Rs. 27.05 Lakhs | Agreement No. 17/KSINC/2021-22 DATED 17/03/2022 | M/s Nevus Infocom | 15-05-2022 | 15-05-2022 | Work Completed | Melba Alias, Project Executive II |
Rs. 2.95 Lakhs | ||||||||||
Dredging at KSINC Boat Yard Thevara | Carrying our dredging work at boat yard for desilting the area | Order no. KSINC/1034/2021 Dated 12/05/2021for an amount of Rs.16,30,300/- | Order No. KSINC/07/ Dredging at KSINC Boat Yard, Thevara dated 14/05/2021 for an amount of Rs.16,30,300/- | Agreement No. 03/KSINC/2021-22 dated 06/08/2021 | Rs. 13.77 Lakhs | 22-09-2021 | Work completed on 04/10/2021 | Work completed and bill settled (Rs. 1396781.78) | Melba Alias, Project Executive II | |
8 | Dismantling the old roofing structure and providing new one at KFT Jetty which is currently being used for Sagararani cruise operations | Order No. P2-7813/2020 dated 29/09/2020 for an amount of Rs. 18,66,028/- (Funded by Department of Tourism) | Order No. KSINC/02/Renovation of KSINC Boat Jetty dated 12/03/2021 for an amount of Rs. 18,66,028/- | Agreement No. 01/KSINC/ 2021-22 dated 21/04/2021 | 16,88,255.00 | 45 days | Work completed on 07/02/2022 | Final bill of Rs. 1861747.44 submitted to DoT and payment effected by DoT | Vishakh R Nair, | |
Renovation of KSINC Boat Jetty at Marine Drive | Project Executive I | |||||||||
9 | Geotechnical investigation for the proposed KSINC cruise terminal and jetty near fine arts hall, Kochi, Ernakulam. | Carrying out geo technical investigation for the proposed cruise terminal for Nefertiti | G.O (Ms) No. 7/2019/CSIND dated 24/09/2019 for an amount of Rs. 7.40 Crores. | -- | Agreement dated 03.06.2019 | 10,15,350/- | 60 days | Work completed on 30/09/2019 | Civil Engineer | |
10 | Dredging work at various sites of KSINC | Carrying out dredging work at KSINC Boat Yard | -- | -- | Agreement dated 15.03.2019 | 7,00,270/- | 40 days | Work completed | Civil Engineer | |
11 | Dredging work at various sites of KSINC | Carrying out dredging at Customs Jetty, Willingdon Island | --- | -- | Agreement dated 13.02.2019 | 11,25,000/- | 28 days | Work completed | Civil Engineer | |
12 | Various Civil Works at KSINC Slipway Complex, Thoppumpady | Construction of compound wall, installation of barbed wire fencing, truss roof for store, parking shed, flooring works, renovation of winch house etc. | --- | --- | Agreement dated 04.01.2018 | 82,42,520/- | 120 days | Work completed | Civil Engineer | |
13 | Dredging work at KSINC Slipway Complex, Thoppumpady | Carrying out dredging at Slipway complex, Thoppumpady | --- | --- | Agreement dated 01.04.2017 | -- | 30 days | Work completed | Civil Engineer | |
14 | Dredging work at KSINC Ferry Terminal, Marine Drive | Carrying out dredging at Ferry Terminal, Marine Drive | --- | --- | Agreement dated 12.01.2017 | -- | --- | Work Completed | Civil Engineer | |
15 | Renovation of Slipway Complex, Thoppumpady | Transfer track rail refitting, construction of toilet and restroom block etc | ---- | --- | Agreement dated 16.12.2016 | 19,43,940/- | 60 days | Work Completed | Civil Engineer | |
16 | Civil maintenance works at KSINC Boat Yard, Thevara | Maintenance of office buildings at Boat Yard | --- | --- | Agreement dated 29.09.2016 | 7,47,465/- | 60 days | Work Completed | Civil Engineer | |
17 | Reconstruction of KSINC Ferry Terminal, Marine Drive | Construction New office building at Ferry terminal jetty. | --- | --- | Agreement dated 06.06.2016 | 1,48,22,900/- | 180 days | Work completed on 30/4/2017 | Civil Engineer |
Interested candidates may submit their application along with copies of testimonials with proof of age and qualification and a recent passport size photograph.